Home / Blog / Templates and examples
Templates and examples

Contracting quote template: BOQs, execution phases, and payments

Proposly team·July 12, 2026·9 min read

A contracting quote is a special kind of proposal: larger amounts, longer timelines, and site variables nobody fully controls. A good proposal is not only a sales tool; it is your first line of defense in any future dispute. This template is built around the clauses that settle contracting disagreements before they begin.

After the cover and understanding summary, including the site address, area, and general description, a contracting proposal is defined by four core sections.

1. The bill of quantities (BOQ), the heart of the proposal

For every item include a sequence number, precise work description, unit, quantity, unit price, and total. Follow three golden rules:

  • The description includes the specification, not only the activity: “Supply and install first-grade 60×60 porcelain tiles,” not simply “tiling.” Flexible descriptions create disputes.
  • State whether quantities are estimates billed according to actual site measurements or fixed lump sums. This sentence resolves many execution disputes.
  • Separate supply from installation wherever the client may provide the materials.

2. Execution phases with a three-way link

Use a table linking the phase, its duration, and its percentage of the contract value. Here is an example for finishing works:

PhaseDurationPercentage
Foundation works3 weeks25%
Plastering and flooring4 weeks30%
Painting and fixtures3 weeks30%
Handover and commissioning1 week15%

This link makes each payment due against a described completion milestone, not merely a calendar date.

3. Payment schedule

Use a 20–30% advance to secure materials, phase payments released after each phase is completed and inspected, and a 10–15% final payment at handover. State a payment period for every certificate, such as five business days after inspection, because delayed payments are a contractor's first cash-flow choke point.

4. Protection clauses: the difference between a professional and an amateur

  • Additional works outside the BOQ are priced through a written change order before execution.
  • Material prices remain valid for a defined period because markets fluctuate.
  • Document client obligations: electricity and water at the site, permits, and selection decisions within defined periods.
  • Agree on a simple mechanism for resolving disputes over the quality of an item.

The contracting template, designed by Abu Bakr Belfaqih

A ready BOQ structure with phases connected to payments. Change only the items and figures.

Use the live template

Fatal contracting proposal mistakes

First mistake: omitting an “unforeseen works” item, especially in renovation. Open a wall and discover what could not be seen; without this clause, you bear the cost alone.
Second mistake: a lump-sum total with no BOQ. Every execution discussion becomes a disagreement with no reference.
Third mistake: accepting “We will agree on payments later.” Later almost never works in your favor.

Conclusion

A strong contracting proposal answers every question that will later arise on site: exactly what, to which specification, when, at what price, and when it is paid. Write the proposal as if it will be read on the day of a dispute, because it will.

The live template is ready to complete

Reserve a place among the first 200 testers and receive the professional plan at half price for life.

Reserve your place

Related articles

Practical guides

How to write a technical and financial proposal that wins the tender? Step-by-step guide

Read article
Practical guides

How should you show pricing: one option or three packages? Where does the discount go?

Read article
Templates and examples

Ready Arabic quote template: core sections that persuade the client + a live template

Read article